The painter \( A \) takes \( 15 \) hours to paint a flat. The painter \( B \) takes \( 12 \) hours to paint the same flat and the painter \( C \) takes \( 10 \) hours to complete the same task. The painter \( A \) starts to paint alone and after \( 2 \) hours joins him the painter \( B \). After the next hour the painter \( C \) starts to paint with them too. How long will all three painters paint together before completing the work?
\( 2\,\mathrm{h}\ 52\,\mathrm{min} \)
\( 3\,\mathrm{h}\ 8\,\mathrm{min} \)
\( 3\,\mathrm{h}\ 24\,\mathrm{min} \)
\( 4\,\mathrm{h} \)